Timeline & Progress

Revive 275 began in July 2021, with anticipated completion in September 2025, including watering and cultivating landscaping.

Construction Progress To Date
96% Complete

2021

I-275 (Will Carlton Road to Northline Road)

  • Repair 10 miles of concrete pavement
  • One lane of I-275 open in each direction

I-275 (Northline Road to Five Mile Road)

  • Culvert replacements and temporary pavement
  • Two lanes of I-275 open in each direction

Bridge rehabilitation

2022

SB I-275 (Northline Road to Five Mile Road)

  • Rebuild 13.5 miles (southbound)
  • Two lanes of I-275 open in each direction

Bridge rehabilitation

2023

NB I-275 (Northline Road to M-14)

  • Rebuild 13.5 miles (northbound)
  • Three lanes of I-275 open in each direction
  • Remove the median crossovers 

Bridge rehabilitation

2024

NB I-275 (M-14 to Five Mile Road)

  • Landscape work
  • Install permanent pavement markings
  • Punch list bridge work
  • Remove temporary emergency pull off lanes

Construction activity listed as complete may require additional punch list construction activity throughout the lifetime of the project.